Friday, June 19, 2015

Bill Has Arrived

Former Tropical Storm Bill rolled through town today. Looks as if most of the rain went south of us, but it still rained all day and we got several inches. By 4:00 pm, most of the rain is now east of us. Heading for Virginia.

Chris showed up and worked in the garage all day. It rained so much that I never got a chance to go out and visit with him. After he had left I went out and he had install a lot of boxes and ran wires. More to do.







Maybe next week the weather will be dry enough to get the stone sills installed and install the gutters.

Mike told me on Wednesday that Bret (roofing) was here on Tuesday and fixed the flashing around the southeast chimney and caulked the nail heads on the sunroom ridge shingles. They do look better. Mike said however that Bret still needs to do some repair work around the eaves. We have had so much rain over the last few weeks, we are confident we have no major leaks on the main house or the new additions. Mike also said that the slate guys came around and he pointed out to them some issues he wanted them to correct.

We took the 12" down rod that we bought with the ceiling fan back to the lighting store and exchanged it with an 18". This should put the fan blades at a height of 8' 6".  I meant to also pickup a remote control, but forgot. I ordered it through Amazon and it should be delivered on Monday.

Thursday, June 18, 2015

Power Up

Around 8:00 am this morning, Chris (electrician) came to the front door and rang the bell. With the garage doors installed, he could not access the sunroom. I met him in back and opened the doors for him. He brought in his tool boxes and appeared to be going to work. About 30 minutes later, I went out to let him know that we had all the exterior wall sconces in the main house along with the ceiling fan. I never got the chance to tell him. Apparently, shortly after arriving, he hauled his tool boxes back out to his truck and departed. I can only assume he got called off for some other service call.

As I was looking out the front door to see if Chris's truck was gone, an Ameren truck drove up. It was a technician to install our new bi-directional power meter. It was a simple matter to make the replacement and it only took about 5 minutes. We did not even lose power.




I sent an email to Eric telling him the meter had been installed and the red tag is on the box. He soon responded saying he would have Jack come by and activate the system. Jack did arrive a little before noon and worked on the activation for several hours. By the time he departed around 3:00 pm, we were making power. With the heavy rain, it was not much power, but it is working. Jack also said he would be the person to move the inverter rack post. As opposed to the message we got from Eric yesterday, saying it would be three weeks before they could move the post, Jack said he hoped to be back tomorrow to get it done.

Here is our power generation for day one. Not too impressive, but it has been raining all day. We peaked out at around 2 kw at 5:00 pm. The system is rated for 9.6 kw.

Wednesday, June 17, 2015

Yesterday and Today

What a day yesterday was!

I ended the day drinking heavily and therefore did not finish my posting.

Yesterday started with the expectation that the garage overhead doors would be installed. When 9:00 am rolled around and it was obvious the overhead door people were not going to be starting early, as expected, I called them. What a surprise!!! We were not only NOT on their schedule for today, but the person I talked with was not sure our doors had even arrived. The lady asked if she could call us back after she did some checking. I was not subtle. I told her that if the doors were not going to be installed today, as scheduled, she needed to have the general manager of the company (Joe) return our call and explain. A few minutes later, Thomas (assistant manager or at least assistant to the manager) called and asked what he could do to make us happy. I was not subtle. Enough said. Bottom line was that Thomas promised the installers would be here this afternoon. I had pretty much given up on them when they showed up around 3:00 pm. They said they would finish before leaving and that might be 9:00 pm tonight. Before I turned in for the night, I left them a bucket of iced beer. This morning, I found the bucket full of empty bottles. They did a nice job.





I really like the direct drive openers as opposed to the openers that hang out in the middle of the garage.


With the doors on, now the electrician can begin the wiring in the garage. Mike said he expected him this afternoon, but he never showed up.

Yesterday morning Eric (solar) came by, as scheduled, to meet us and look at the inverter rack.



He agreed the installation was not acceptable, which alleviated the necessity of my reminding him of the humiliating performance of his company on this project. We agreed that there were two options. First option would be to move the two boxes so that they are centered between the vertical posts. This is what I had assumed they would do. The second option, suggested by Eric, was to leave the boxes where they are and move the right vertical post to the left. I thought that was a great idea and, while either option would be acceptable to us, I preferred moving the post. However, it would have to be accomplished before we poured the slab around the rack since the post has a concrete footing. Don't know when slab will be poured, but hopefully, it will not be long from now. Eric said he would talk with the project manager (Rick) and determine which option would be used. I got a note from Eric today saying he talked with Rick and "we seem to all agree now" and the work is tentatively scheduled for July 8 (three weeks from now). I wrote back saying that, while it is great that we are all in agreement, I still don't know which option they have selected. If they are going to move the post, I will pass on to Mike the projected schedule to see the slab is expected to be poured prior to that date. If they are going to move the boxes, they can do that anytime they wish to be paid the final payment. Eric responded they intended to move the post. I re-emphasized the need to have this done before we pour the slab and we are not willing to delay pouring the slab. I will send Mike a note with the July 8 proposal and see if he thinks the slab will be ready to pour before then.

We also had Mike and Nate show up. They did not do anything, but were there to meet with Bob (cabinetry) and Bob (landscaping). Bob (landscaping) never showed up. Bob (cabinetry) had shown up early and we visited with him before Mike arrived. Bob and T reviewed and discussed the sunroom staining done by Jerry. They agreed it was OK. One of the questions Bob had asked me in a note was whether his company or Mike would do the actual installation work. When Mike arrived, Mike seemed very interested in letting Bob's craftsmen do the installation. Bob said he would go back and look at their schedule. Bob also told us that, on his way to our place, he dropped off the template to the stained glass shop for the bar cabinet doors.

Yesterday, I opened all the new wall sconces we brought home on Monday and assembled all of them to ensure they were not defective. The four new ones look good. I also opened the two replacements we exchanged for defective ones. These had supposedly been checked at the store before they were given to us. Guess what? One was defective. I called and told them I was bringing it back and that I would want to open the next replacement and inspect it before bringing it home. This is what we did and now we finally have all nine exterior wall sconces.

This afternoon, we got a note from Kim (stained glass) saying they had the glass cut and were ready to start putting it together. Before they started however, they wanted us to see it and give them permission to proceed. I showed the photo to T and she liked it. I responded to Kim to proceed with leading it together.


Kim asked if we would be willing, once everything is finished, to permit them to take some promotional photos showing their contributions to our project. We told them we would be proud to allow that.

Some time ago, we told Bob (landscaping) that we may want to put a light post somewhere around the chess board patio. Monday, we got a note from Bob (landscaping) saying that we still needed to decide where to put this post so the electrician could run power to the area. T and I got the landscaping drawing and decided there were two potential locations. I drew these spots on the drawings, sent it out with a note to Bob and discussed with Mike about having the electrician run power to both locations. Mike said he sent my drawings on to Chris (electrician). We never got a response from Bob.


Monday, June 15, 2015

Cupola One

I was not surprised the roofers, the slaters or the brick layers did not show up today. They were forecasting heavy rain this afternoon and Mike had already forewarned me. With the forecast for heavy rain for the next few days, I am not banking on finishing the exterior this week.

Other than a brief period around noon when it did rain heavily for about an hour, the weather today was sunny and humid.

Mike and Nate arrived around 7:00 am got the garage cupola installed.


Base in Place

Body in Place
 We had an appointment to visit Bob's (cabinetry) shop at noon, so we were not around when they put  on the copper roof. Due to its weight, Mike said he had additional help coming.





Mike cut a hole in the garage roof underneath the cupola as I requested. We'll have a chance over the next couple of days to see if we are going to have leaks.

We have decided to defer the installation of an exhaust fan underneath the cupola for now. Mike believes we will we be happy with the amount of natural draft we get due to the vented soffits and roof ridge vents.

Hole in Garage Roof


It appears they got the weather vane's compass correctly oriented.

We did visit Bob's cabinetry shop and met Don. The bar cabinets looked good. The visible fronts are the Sapele while the interiors are maple. They are still waiting for the doors to arrive in the next day or two. Don said they should start the wood finishing process next week. We asked Don about the status of the mantel piece. He was unaware. Later, Bob wrote saying that Don had not seen the drawings of the mantel yet but the materials should be here within the next week. Coincidentally, before leaving this morning, we got a call from Kim (stained glass) asking about the status of the bar cabinet door. They are getting close to wanting to start on the stained glass for the doors and need the final dimensions. I told her we were heading up to the cabinetry shop and, if possible, we would bring a door back with us for them to measure. Since the doors had not arrived, we told Kim that Bob should be getting with her in the next couple of days with an actual template of the doors.

Bar Cabinetry Without Doors
I also sent Bob some photos of the staining done in the sunroom. I told him the ceiling and trusses turned out darker and less uniform than we had expected. Further, if there were any questions in his mind before starting the finishing of the Sapele bar and paneling, he should come out and look for himself. He responded that he would be out tomorrow to look for himself.

I got a note from Eric (solar) early this morning saying he wanted to come out to meet us tomorrow and talk about the inverter rack. I responded that any time is fine, just let us know when to expect him. I finally got a reply around 5:30 pm saying he will be here tomorrow morning at 10:30 am.

We also never got the confirmation call we were told to expect from the Overhead Door company regarding tomorrow's scheduled garage door installation. These people have not been very impressive.

Upon leaving Bob's shop, T and I stopped by our local lighting store to pick up the garage south side exterior wall sconces, exchange two of the wall sconces we had picked up a couple of weeks ago and to decide on the sunroom ceiling fan. We accomplished all of the above. The fan we selected is the Emerson Zurich. We decided to not purchase the light attachment yet.

Ceiling Fan
The garage wall sconces we picked up are being discontinued. Their "normal" price was $97.00 each, but the close out price was $17.00 each. This is the same design, but a little bit smaller, than the five we purchased a couple of weeks ago (two for the north side of the garage, two for the south door of the sunroom and one for the west door of the sunroom). Those were also be discontinued and were normally $149 each, on sale for $25 each. That's nine lamps normally selling for $1,133.00 for just $193.00. Call me cheap, but I've been called worse and I'll accept those economics any day!

Garage South Wall Sconces