Friday, October 17, 2014

Clean Up

"Concrete" Mike's crew showed up early this morning to complete the haul off of the remnants of the foundation framing materials. Next week the back filling and leveling will begin.



No further work on the basement water systems today. They should be back next week. The domestic hot water heater continues to work well. We have both noticed that it takes significantly longer for hot water to "arrive" at the kitchen sink. Something we will get used to.

Now the surprise of the day,

We received an email from Betsy (solar) this afternoon warning us that she would be sending us a Change Order (CO) for approval along with the cost associated with that CO. She explained this was due to our decision (made about a month ago) to locate the inverters outside, instead of in the basement. She went on to say that "the increase in price shouldn't be too bad". The last time I was told something like this, and from this company, the price increased by 15%. I therefore was slightly perturbed. I sent a note back to Betsy asking how there could be a change order when the contract did not specify the inverters were to be located in the basement. I strongly suggested that we needed to talk....soon. She called shortly thereafter and we talked for quite awhile. Overall, it was an open, honest and amiable conversation.

Betsy stated that the initial proposal, while it may not have specified, assumed the inverters would be located somewhere inside (either in the garage or the basement). She went on to state that locating the inverters outside would result in an efficiency reduction.
WAIT A MINUTE....TIME OUT!
I reminder her that when we were originally discussing the location of the inverters (a month ago), we were not informed that locating them outside was even an option. We only found this out by doing our own on-line research. Once we became aware of this option, we initiated an email discussion with Drew (their project manager) regarding its feasibility. Betsy was copied on these emails. Drew stated that locating the inverters outside was rarely done because "most people don't want to see them all the time". Since this was not a concern to us, we responded that, "We are leaning toward an outside location" and "If there are other considerations which need to be taken into account concerning the general location of the inverter panel or the required slab, please let me know as soon as possible". Finally, upon deciding on the outside location, we told Drew that "When we get closer to the point of pouring the slab, we'll be in touch with you to ensure it is acceptable". Late last week, I sent a note to Betsy and Drew informing them that we are close to being ready to pour the slab, on which the inverters will be mounted, and that they must ensure their requirements are known to "Our" Mike.

Now, a month after the decision was made to locate the inverters outside, based upon the information provided to us, we are learning that there ARE other issues, namely cost and efficiency. Betsy also acknowledged that, despite my previous requests, their company had not communicated with either our general contractor or our electrical contractor. Our project had "fallen through a crack". 

Betsy said she would develop information regarding the following: 1) any additional costs of locating the inverters outside; 2) any impact on the equipment durability or efficiency associated with the outside location; 3) a review of the interface of the solar electrical system with the rest of the project's craft contractors. I told her that with this information, we will be able to decide whether we will continue with the solar part of the project at all, and if so, where the inverters will be located.

Before we signed the contract, we had warned the solar company that we would not tolerate foreseeable "surprises" during the course of the project. While Betsy acknowledged this issue may have "fallen through a crack", her company "was not trying to screw us" (her words). I assured her that we wanted to follow through with the solar part of our project, but it is a discretionary part of that project. If they lose our confidence, the solar portion will come to a quick end.

Thursday, October 16, 2014

We're In Hot Water Now!

Today was a good day. The weather was perfect...cool and sunny. "Concrete" Mike sent a crew of three to load the foundation wall frames and haul them off. "Our" Mike said "Bobcat" Tom will be here on Monday to begin back filling the trenches. We now have a better view of the layout of the buildings. Once the back filling is complete, we will really be able to envision it! Mark (inside plumbing) stopped by and said he was expecting to run utilities out to the garage next week. We have a good chance of really nice weather for the next week to 10 days. Hopefully, we'll take advantage of it.













Vern's boys finished the new incoming domestic water line. They will  be back probably Monday to remove the steel cover plates in the street. The City is responsible for application of new asphalt.




New Shutoff Valve









Tap into Water Main




New Basement Shutoff Valve and New Line


















John and Tim finished the new on-demand domestic hot water heater installation. T has already tested it, filling the tub for a delightful soak. It seemed to work well.

Frank joined John and Tim for awhile today and we talked about the new boiler, to be installed next. Frank gave me a piping drawing and a sketch of the floor plumbing for the radiant floor heating. There will be three zones and will include heating of the connecting porch between the house and the sunroom. The floor loops are on 8" centers and will be embedded in the concrete floor slab.

Wednesday, October 15, 2014

Lot's of Noise Today

As predicted, there was light rain on and off throughout the night. By day break, it had stopped, but continued to mist throughout the day. Tonight, the clouds are supposed to move out of the area. The forecast is for no rain for the next several days with clear, sunny skies. Good weather to cure concrete.

"Concrete" Mike's crew of two arrived just after day break and began removing the foundation wall forms. It appears they got most, if not all of the forms broken away from the new walls, but they still need to load up the panels and haul them off. Maybe tomorrow. "Our" Mike showed up and said the concrete looks good to him. Our architect (Tyler) warned me that the building footprints will look small once the foundations are in place. He was correct.


John and Tim (HVAC) arrived and continued in the basement on the water systems. When John left for the day, he told T that he expected to complete the domestic hot water system tomorrow.

The big event of the day was the return of Vern's crew (outdoor plumbing) to begin running our new incoming domestic water line. We will abandon the existing 1" lead line and commission a 1-1/2" copper line. They dug one hole in our yard down to the shutoff valve while chiseling out a "window" in the stone foundation of our basement. The cover to the shutoff valve in the yard was buried about 8" under the lawn surface, between the sidewalk and the street. Excavation down to the valve itself revealed that the ball valve was only about one-half open. Probably has been that way for decades. They then proceeded to bore a hole from the basement "window" to the hole at the street using a pneumatic "mole". They jack hammered holes on both sides of the street. The one on our side was to expose a natural gas line and another City water line. The hole on the other side of the street is where the actual tie-in to another City water main will be made. The entire process should be completed tomorrow and will represent the last major infrastructure upgrade mandated by the City.



Chiseling the "window" in stone foundation
New Copper Water Line

The Mole and the old lead line

















Between the jackhammers in the street, the chiseling, drilling and hammering in the basement and the pounding in the backyard, it was a very noisy and nerve rattling day. But, T is home after almost three weeks absence. I have missed her.

Tuesday, October 14, 2014

Slow But Steady

Other than "Concrete" Mike showing up to pump water out of the trenches, nothing happened outside today. We had a cool and misty day. Little or no measurable rainfall, but not conducive to drying out either. While I have not been told it will happen, I am expecting "Concrete" Mike to have his crew back maybe tomorrow to remove the foundation frames. "Our" Mike told me that they had to rent some additional narrow gauge frames to use around the bay foundation, so I'm sure they are anxious to get those returned.

John and Tim (HVAC) returned today to continue work on the water systems in the basement and will be back tomorrow. Still not finished with the domestic hot water heater. They installed the framing for the radiant floor boiler today. I expect they have several more days of work ahead of them. T is arriving home late tonight from Texas. I was hoping to have time to test the domestic water heater before she arrived so, if it didn't work well, I could leave town. However, I am more and more confident it will work very well.

This afternoon, "Our" Mike forwarded to me an email from Vern's company (outside plumbing) with their updated plan to start the incoming domestic water line tomorrow (Wednesday), weather permitting. The forecast is improving with only a 30% chance of rain tonight and dropping to 0% tomorrow. The forecast starting Thursday, and through the next 10 days, is for clear, dry and cool weather. If true, next week we should be able to get the trenches back filled and level out the back yard. We also still need to re-install the garage downspout laterals that weren't properly located initially and had to be removed for the foundation work.

Monday, October 13, 2014

A Milestone - Foundation Wall Poured

Yesterday (Sunday), "Concrete" Mike stopped by and looked over the backyard. He did not stay long. The weather forecast for today (Monday) was (and still is) 100% chance of rain with possibly strong thunderstorms after noon. Therefore, I was amazed when "Concrete" Mike and his crew showed up at 7:00 am this morning. The pump trailer showed up at 8:00 am and started laying the transfer conduit and hose. By 9:30 am they had completed the remaining framing work and were pouring concrete. The weather cooperated with only a couple of light showers during the morning. By 1:00 pm, they were done and gone. They should be back tomorrow or Wednesday to remove the forms.

Talking today with "Our" Mike, with the weather forecast being fair and dry beginning on Thursday of this week, he is arranging to have "Bobcat" Tom come next week to back fill the trenches. Tom will also be trenching for the power and utility lines and excavating for the slab on the east side of the house for the relocation of the existing AC condensers and the solar panel inverters.



John (HVAC) showed up around 7:00 am also to continue the installation of the domestic hot water heater. Tim arrived later to assist. They were not able to complete the installation today after all. They will be back tomorrow. We have a new air intake/exhaust outlet vent on the west side of the house. It can be painted.


Over the weekend, I did a test of filling the tub with hot water. Bottom line is that I am now estimating we consume energy at the rate of 150,000 BTU/hr when T fills the tub (60 gallons over 6.5 minutes with an initial hot water temperature of 127⁰F, an incoming water of 67⁰F and a resulting tub water temperature of 101⁰F). Since this is half of what I had estimated before, if correct, the new heater (rated for 200,000 BTU/hr) should do fine. 

Vern (outside plumbing) was expected to start the replacement of the incoming water line today, but did not show up.

Over this past weekend I sent a note to the Betsy (solar) regarding the Utility Net Metering Agreement application we signed in the first week of September. Approval of this agreement, by the utility company, is the first step in getting the solar system connected to the grid. My understanding, when we signed the contract, was that the solar company would take care of filing the application and we could expect to hear directly from the utility company in a couple of weeks. We have not heard anything yet, hence my email. In response to my email, Betsy wrote back indicating that they have not filed the application, and were waiting for us to decide where we were going to locate the inverter panels (why this would impact the application, I don't understand).  I reminded Betsy that several weeks ago we discussed this issue with Drew (copied Betsy) and indicated our desire to locate these panels outside on the east side of the house. I noted that we are expecting to be trenching for the utility lines and pouring slabs for the inverters in the next week or so. I also reinforced to her that we expect them to stay in contact with "Our" Mike to ensure the requirements of the solar part of the project are addressed and folded into the scheduled. They also have access to this blog.