For the first time since our return, I talked with Mike this morning when he and Nate showed up to work. They worked all day. Cannot see much of what they did, but we are at the point where they are working on the details.
Mike confirmed he had not discussed the solar inverters with the solar company. I henceforth sent another note to Eric (solar) informing him that I had canceled the payment I had scheduled for later this week. I also called Eric and we had a nice chat. Erick confirmed their internal communications failed and they would modify the inverters to conform to our expectations. While this is what he told me prior to our departure, I have every expectation he will follow through. This is not yet holding up anything since we are waiting on Ameren (local electric utility) to install the new bidirectional meter before we can power up the system.
Before Mike arrived this morning, I chatted with Nate. I asked him if the brick layers were finished. He said (correctly) that he did not think they were, but then said something about replacing the bricks around the hot tub bay so that it was circular. I had noticed that the bricks conformed to the nine windows around the bay, but did not realize it was supposed to be a smooth circle. When Mike arrived, I asked Mike about this. He said that Tyler (architect) had stopped by while we were gone and suggested that the brick work around the bay was supposed to be a smooth circle. Mike said this would have necessitated a wider foundation to which, according to Mike, Tyler asked if the foundation was installed correctly. Long story short, it is fine.
Mike said the cut stone for the interior chimney breast had arrived and, I assume, is being held at the materials store, much like the porcelain floor tiles.
Mike said the limestone window sills for both the garage and sunroom should be here on June 15.
I asked Mike about the Tigerwood for the decking. He said he needs to order it. I did confirm with him that he will put clips in the decking around the hot tub and on the porches, but not on the flooring in the connecting porch.
Mike confirmed that the roofing is still not complete. No payment due then.
I asked about the east slab and the garage approach apron. Mike said the landscaper was going to wait until the guttering is installed before pouring any concrete. This is NOT what we had agree to. I did not challenge Mike but will bring it up again.
I called the Overhead Door company this morning and, after chastising them for their incompetence, scheduled them to install our garage overhead doors on Tuesday, June 16.
I pointed out to Mike that there were supposed to be a sunroom ventilation louver and fan control on the connecting porch. Mike said they would be able to install that. He then surprised me when he asked when the sunroom ventilation fan was supposed to arrive because he was anxious to get the cupolas installed. I reminded him that the electrician was supposed to have ordered that. He suddenly "remembered", which makes me think he might have forgotten to let the electrician know.
T and I went down to our favorite lighting dealer to pick up the five exterior wall scones we had order prior to our departure. We were very proud to have found five scones which were being discontinued and selling for 25% of their normal selling price.
We also picked out four other scones to be used on the south side of the garage. These are similar and being discontinued as well. They were only 15% of their normal sales price. We will pick these up in a couple of days. When we got the five scones home, we opened them up and found two of them defective (made in China). I called the dealer and they said we could pick up replacements when we came in for the four we ordered today.
The bat pendent lamp arrived today. It will be VERY interesting hanging above the bar.
We booked out next cruise to Barcelona today.