The slate installers returned, finished the west garage gable and started on the east gable. As I expected, they did not bring enough slate shingles to finish the garage let alone the sunroom. It is a slower process than I expected. It goes fairly quickly until they have to start trimming to follow the angle of the roof. Not sure when they will return.
Slate on west garage gable |
Slate going on east garage gable |
I asked Mike this morning if he had heard back from the brick layers regarding the specific brick they intend to use next week. Mike said he had not. I suggested to Mike that we need to ensure T has a chance to review what they intend to use before they go to the trouble of delivering it. Mike agreed, but at the end of the day, we still had not seen a sample.
We got a call from Bobby (fireplace) to tell us that he had talked with Mike and they intend to be here next Thursday to install the fireplace.
The plumber showed up early again today to continue working on the garage plumbing. He installed the small hot water heater above the northeast sink.
Today we placed an order for the bar appliances (refrigerator, dishwasher and ice maker). We had previously purchased the garbage disposal. We also placed an order for the copper sink. We still need to decide on the faucet.
The roofers did not reappear today.